Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?

1 Answer

4 votes

Answer:

identify the critical path

Step-by-step explanation:

Based on the information provided, the logical next step for Emily would be to identify the critical path. This means identifying the sequence of project network activities that add up to the longest overall duration which in term will reveal the shortest time possible to complete this project through unnecessary parts within the critical path, and will allow her to meet the imposed deadline.