A queuing theory analysis for the Department of Motor Vehicles determines that customers typically wait for 8 minutes and that the agency should strive never to exceed more than 5 customers in a single line. What is the maximum amount of time that customers should be expected to wait?

User Jangorecki
by
3.6k points

1 Answer

5 votes

Answer: 40 minutes

Step-by-step explanation:

A queueing theory is simply the study of queues or waiting lines. From the question, we are informed that a queuing theory analysis for the Department of Motor Vehicles determines that customers typically wait for 8 minutes and that the agency should strive never to exceed more than 5 customers in a single line.

The maximum amount of time that customers should be expected to wait will be the wait time for a customers multiplied by the number of customers on a queue. This will be:

= 5 × 8 minutes

= 40 minutes