John can clear a lot in 1.5 hours. His partner can do the same job in 4.5 hours. How long will it take them to clear the lot working together?

User Joealba
by
8.1k points

1 Answer

1 vote

Answer:

1.125 h = 1h 7.5 min = 1 h 7 min 30 sec

Explanation:

John makes 1/1.5 work per h.

His partner makes 1/4.5 work per h.

Together they make (1/1.5 + 1/4.5) = (3/4.5 + 1/4.5) = 4/4.5 work per h.

They will work

1 : 4/4.5 = 4.5/4 = 1.125 h = 1 h + 0.125 h = 1h + 0.125h*60min/1h =

=1h 7.5 min = 1 h 7 min 30 sec