201k views
0 votes
When activity times are uncertain:______.

a. assume they are normally distributed.
b. calculate the expected time, using (a 4m b)/6.
c. use the most likely time.
d. calculate the expected time, using (a m b)/3.

User Parkar
by
3.7k points

1 Answer

5 votes

Answer:

b. calculate the expected time, using (a 4m b)/6.

Explanation:

In project management, when activity times are uncertain, the appropriate approach is to calculate the expected time using the following expression:


T =(a+4m+b)/(6)

Where 'a' is the most optimistic outcome, 'm' is the most likely time, and 'b' is the most pessimistic outcome.

Therefore, the answer is b. calculate the expected time, using (a 4m b)/6.

User Kianoush Dortaj
by
4.0k points