Answer:
Variable cost per hour= $0.13
Step-by-step explanation:
Giving the following information:
March $3,018 15,239
April 2,628 9,504
May 2,857 11,534
June 3,730 18,045
To calculate the unitary variable cost under the high-low method, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (3,730 - 2,628) / (18,045 - 9,504)
Variable cost per unit= $0.13 per hour