Answer: c. 5 days, 7 workers
Explanation: With the project requirements provided, and with the least of number of resources working on the task not less than the number of those assigned to the task.
The least amount of time for the project to complete would be approximately 5 days, and the resources needed to complete the task would be approximately 7 workers.