Answer:
Predetermined manufacturing overhead rate= $240 per order
Step-by-step explanation:
Giving the following information:
Ordering and Receiving Orders $ 120,000 500 orders
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 120,000/500
Predetermined manufacturing overhead rate= $240 per order