Which employee labor rate is typically used to produce a project budget?

User Daniely
by
4.3k points

1 Answer

4 votes

Answer:

Billable rates

Explanation:

The Billable Rate is the amount of money i,e to be charged per employee per labor per hour that the client has to pay with regard to product and service charged. It also analyze how much the business organization makes from the sale of product and services they are offering to the client

The billable cost is therefore factored in the budget for the project.

So, the correct answer is billable rates