Answer: $2.81 per machine hour
Step-by-step explanation:
Wages and salaries $ 423,000
Activity cost pools 10%
Allocated amount = 10% of $423000
= 0.1 × 423000
= $42,300
Depreciation = $112,000
Activity cost pools 10%
Allocated amount = 10% of 112,000
= 0.1 × 112000
= $11200
Occupancy 154,000
Activity cost pools 20%
Allocated amount = 20% of 154000
= 0.2 × 154000
= $30800
Total allocated amount = $42300 + $11200 + $30800 = $84300
The cost hour is the machine hour which is 30,000
Rate per machine hour = total allocated amount/machine hour
= 84300/30000
= $2.81 per machine hour