Answer:
$43,988
Step-by-step explanation:
The computation of the direct labor cost is shown below:
Production 51,000 candles
Multiply by Minute per candle 3
Candle 153,000 minutes per candle
Convert minutes to hours ÷ 60 minute
Molding hours 2,550
Multiply by Labor cost per hour $17,.25
Total direct labor cost $43,987.50
Hence, the direct labor cost for the month of January is $43,988