Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incur $800,000 of overhead during the next period, and expects to use 50,000 labor hours at a cost of $10.00 per hour. What is Cosi Company's predetermined overhead rate?

1 Answer

4 votes

Answer:

160%

Step-by-step explanation:

From the question above Cosi company is expected to incur $800,000 of overhead during the next period.

They are also expected to use 50,000 labor hours at a cost of $10 per hour

The first step is to find the estimated direct labor costs

= 50,000 × $10

= $500,000

Estimated direct labor cost= $500,000

The next step is to find the estimated overhead rate

Estimated overhead rate= Estimated overhead/Estimated direct labor costs

= 800,000/500,000

= 1.6 × 100

= 160%

Hence the predetermined overhead rate for Cosi company is 160%