Answer:
D. All of the alternatives are true.
Step-by-step explanation:
Crash activity time are been used in the in different organisations for different reasons. In the case, above the mentioned conditions in all options are been put to consideration. Because in its determination, one has to analyze thoroughly its critical path method in its first step; here the tasks are been shortened before being tackled. Secondly, you identify the newer critical ways in dealing of the things.
Also, normal activity costs and costs under maximum crashing are been made known. Therefore, all options above appear to be one of the steps in critical ways of determining crash activity time.