Answer:
Predetermined manufacturing overhead rate= $50 per machine-hour
Step-by-step explanation:
Giving the following information:
Estimated overhead costs= $3,400,000 for indirect labor
Estimated overhead costs= $850,000 for factory utilities.
85,000 machine hours are planned for this next year
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (3,400,000 + 850,000) / 85,000
Predetermined manufacturing overhead rate= $50 per machine-hour