Answer:
Option A. Variable costs of $56,700 and $43,900 of fixed costs
Step-by-step explanation:
Given:
Jase Manufacturing Co.'s static budget at 7,800 units of production includes;
Direct labor = $39,000
Electric power = $3,120
Total fixed costs= $43,900
Variable costs = [$(39,000 + 3,120) ÷ 7800] × 10,500= $56,700