Answer:
$518,700
Explanation:
For the computation of unadjusted cost of goods sold first we need to find out the total cost of Job F21X and cost per unit which is shown below:-
The Total cost of Job F21X = Beginning balance + Direct materials + Direct labor + Manufacturing overhead applied
= $45,150 + $363,300 + $161,700 + $207,900
= $778,050
Cost per unit = Total cost of Job F21X ÷ Number of units
= $778,050 ÷ 10,500
= $74.10
Cost of goods sold = Completed units from Job F21X × Cost per unit
= 7,000 × $74.10
= $518,700