101k views
3 votes
2. Risks ____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.

User Efajardo
by
7.9k points

1 Answer

4 votes

Answer:

Risk on the critical path should be given higher priority than activities that are not part of the critical path, or that have a positive slack.

This is because incurring in a riks that is on the critical path can seriously alter the schedule of a project, to the point that the project could be delayed or put off.

User Chau Chee Yang
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.