Answer:
Predetermined manufacturing overhead rate= $21 per inspections
Step-by-step explanation:
Giving the following information:
For its inspecting cost pool, Ellis Company expected overhead cost of $45,150 and 2,150 inspections.
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 45,150/2,150
Predetermined manufacturing overhead rate= $21 per inspections