Answer:
Unitary variable cost= $1.72
Step-by-step explanation:
Giving the following information:
Mcleod, Inc. incurred fixed costs of $400,000.
Total costs= $450,000
Units produced= 59,000
First, we need to calculate the total variable cost:
Total variable cost= total cost - total fixed cost
Total variable cost= 450,000 - 400,000
Total variable cost= 50,000
Now, the unitary variable cost:
unitary variable cost= 50,000/29,000