Answer:
$84,700
Explanation:
The computation of manufacturing overhead in the planning budget for July is shown below:-
Manufacturing overhead in the planning budget = Manufacturing overhead per month + Budgeted hours × Budgeted rate
= $25,700 + 5,900 × $10
= $25,700 + $59,000
= $84,700
Therefore for computing the manufacturing overhead in the planning budget for July we simply applied the above formula.