Answer:
Direct labor= $51,840
Step-by-step explanation:
Giving the following information:
Standard Hours= 27 minutes
Standard Rate per Hour= $6
Standard Cost= $2.70
During August, 9,260 hours of direct labor time were needed to make 19,200 units of the Jogging Mate.
We need to determine the standard cost for 19,200 units.
Direct labor= standard cost per unit*number of units
Direct labor= 2.7*19,200= $51,840