Answer:
1. Total cost of purchases for the month
- = actual purchases x actual price = 200,000 pages x $0.175 per page = $35,000
2. Materials price variance
- = (actual unit cost - standard unit cost) x actual quantity used = ($0.175 - $0.17) x 185,000 = $925 unfavorable
3. Materials quantity variance
= (actual quantity used - standard quantity allowed) x standard price = (185,000 - 170,000) x $0.17 = $2,550 unfavorable
4. Net materials variance
- = materials price variance + materials quantity variance = $925 + $2,550 = $3,475 unfavorable
Step-by-step explanation:
Actual purchase price $0.175 per page
Standard quantity allowed for production 170,000 pages
Actual quantity purchased during month 200,000 pages
Actual quantity used during month 185,000 pages
Standard price per page $0.17 per page