Answer:
In this case, the liquidated damages are too high and can be considered a penalty instead. Unreasonable penalties, like this one, can be considered unenforceable since they are treated as coercive measures to force the contractor to finish early. Big Bad Wolf would probably have to pay only the actual loss suffered by Johnny Pig ($1,000), instead of the amount stated as liquidated damages ($1,800).