Both the Army and Marine Corps have a capability need to procure additional helicopters beyond the number specified in the current contract; the helicopter program is currently in production. What cost estimating technique would the services most likely use as a basis for requesting the funding to pay for the additional aircraft?

User Jose Reyes
by
5.4k points

1 Answer

2 votes

Answer:

Actual Cost

Step-by-step explanation:

Based on the information provided it can be said that the estimating technique needed would be the actual cost technique. This refers to calculating the actual expenditure made for acquiring a specific asset. This includes all of the expenses that the supplier has invoiced as well as the costs incurred to set up, test and deliver the asset in question. Therefore in a situation such as this one the actual cost technique will be used as a basis for the amount of funding to pay.