Why is Earned Value a very powerful tool? Answer: It combines the cost, scope, and ____________ as an integrated tool to calculate project performance. It also allows us to do _______________ under different estimating assumptions as discussed earlier.

User Xcramps
by
8.0k points

1 Answer

4 votes
Answers
1) Time
2) cost analysis or performance measurement.

Step-by-step explanation


Earned value — it integrates cost, time and the work done (or scope) and can be used to forecast future performance and project completion dates and costs...