Answer:
The correct answer is B.
Step-by-step explanation:
Giving the following information:
Units= 770,000
Standard machine hours= 0.85 per unit
Estimated: Department 1 Department 2
Manufacturing overhead costs $3,141,500 $1,571,000
Machine hours 267,000 MH 192,000 MH
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (3,141,500 + 1,571,000) / (267,000 + 192,000)
Predetermined manufacturing overhead rate= 4,712,500 / 459,000
Predetermined manufacturing overhead rate= $10.27 per machine hour
Now, we can calculate the allocated overhead per unit:
Allocated overhead per unit= 10.27*0.85= $8.73