Answer:
The reported cost of the land = $99,560
Step-by-step explanation:
In order to calculate the cost of the land, it is important to note that the amount recorded as cost of the land, includes the actual amount paid as the market price of the land, including all the necessary costs incurred to make the land ready for use. These include: attorney's fees, cost of demolition of old properties, broker's fees etc.
To calculate the net cost of the land, let us identify all the transactions done in the purchase of the land. This is done as follows:
market value of land = $ 79,000
cost of demolition = $ 8,000
additional expenses = $ 1,160
attorney's fee = $ 4,400
broker's fee = $ 8,660
salvaged materials = $ 1,660 (minus)
Total = $ 99,560
Note that the amount gotten from sale of salvaged materials is subtracted from the cost of land, because it is an income, not expenditure, while the architect's fee is not used in the calculation because, it doesn't meet the criteria for cost of land, instead it is part of the cost of building after the acquisition of the land.