Answer: c.$71 per machine hour
Step-by-step explanation:
The Pre-determined Overhead rate is the rate Thomlin Company forecasted that the company would incur total overhead for the current year.
They forecasted total overhead of $11,597,000 with 164,000 total machine hours.
Since the rate is based on Machine Hours the rate would be,
= Total Forecasted Overhead / Total Forecasted Machine Hours
= 11,597,000 / 164,000
= 70.71
= $71