Answer:
354 hours
Step-by-step explanation:
Direct material cost = $7,250
Actual manufacturing overhead cost = $40,800
Applied manufacturing overhead cost = $40,800
The given value if work process at end of May(May 30) = $16,808 and & $7,250 was used as direct material cost.
Thus, remaining labor and overhead = $16,808 - $7,250 = $9,558
Given an overhead rate of $12 per hour and labor rate of $15 per hour
Overhead rate + labor rate = $12 + $15 = $27 per hour
Direct labour hours worked =
$9,558 ÷ $27 = 354 hours
Therefore the actual direct labor hours worked during may is 354 hours
None of the given option is correct. They are stated in $ and the values are unrealistic.