Answer:
Option A is correct
Cost per equivalent unit for material - $3
Step-by-step explanation:
Cost per equivalent unit = Total direct material cost / Total equivalent unit
Equivalent units of materials
Item Equivalent unit
Opening inventory 3000×0% = 0
Fully worked 8,500× 100% = 8,500
Closing inventory 1,500 ×100%= 1,500
Total equivalent units 10,000
Notes:
Fully worked represent the units started and completed in July
Fully worked = newly introduced units in July - Closing inventory in July
Fully worked = 10,000 -1500 = 8,500
Cost per equivalent unit = Total direct material cost / Total equivalent unit
= 30,000/10,000=$3
Cost per equivalent unit for material =$3