Answer:
The answer is below
Step-by-step explanation:
The first option of seeing the contract run as per the terms agreed at the beginning.
This is because the alternative of paying the 35000 at an interest of 10% for the 12 months would cost more by 1,342.
Given that;
FV= PV(1+r)^{n}
FV=PV(1+r)^n
Where FV = Future value, PV = Present value, r = annual interest rate
n = number of periods
Hence, we have;
First option
FV= 35000(1+0.02)^{8}
FV=35000(1+0.02)^8
FV=41,008
Second option
FV=35000(1+0.1)^{2}
FV=35000(1+0.1)^2
FV= 42,350