102k views
5 votes
Your firm is considering two different projects that are mutually exclusiveand they will be replaced once the project is over. Given a required return of 12%, which project should your firm undertake(Hint: you should calculate the EAA to decide which is the better project for this problem)

User Ivankeller
by
5.4k points

1 Answer

5 votes

Your firm is considering two different projects that are mutually exclusiveand they will be replaced once the project is over. Given a required return of 12%, which project should your firm undertake(Hint: you should calculate the EAA to decide which is the better project for this problem)

Time 0 1 2 3

Project A -25,000 15,000 20,000 20,000

Project B -25,000 11,000 11,000 11,000

Answer:

Project A should be better and should be accepted because it produces a higher EAA of $7,732.5746

Step-by-step explanation:

NPV = PV of cash inflow- Initial cost

PV of cash inflow = 15,000×1.12^(-1) + 20,000×1.12^(-2) + 20,000×1.12^(-3)=43,572.33

NPV = 43,572.33 -25,000 =18572.33965

EAA= NPV /Annuity factor

= 18572.339/2.401831268 = 7732.57468

Project B

PV of annuity = A× (1- (1+r)^(-n))/r

= 11,000× (1-1.12^(-4))/0.12=33410.84281

NPV = 33410.84281 - 25,000= 8410.842813

EAA = 8410.842/3.03734 =2769.139

Project A should be better and should be accepted because it produces a higher EAA of $7,732.5746

User AMGMNPLK
by
5.3k points