Answer:
Step-by-step explanation:
Job 11-101=$3,880
Job 11-102= $2,630
Job 11-103= $2,080
Job 11-104= $3,190
Job 11-105= $2,080
Total 13,860
Direct labor rate = $18
Predetermined overhead rate = $22
Direct labor hour = 13,860/18 = 770 hours
Applied factory overhead rate = 770 *22 = $16,940
Factory labor cost
Dr Cr
Work in progress 13,860
Factory Overhead 18,000
Wages payable 31,860
Factory Overhead
Work in progress 16,940
Factory overhead 16,940