Answer:
total budgeted costs = $189,400
budgeted production = 1,000 units
standard rate = $189,400 / 1,000 = $189.40 per unit
total actual costs = $197,200
actual production = 1,120 units
actual rate = $197,200 / 1,120 = $176.07 per unit
- total fixed overhead variance = actual overhead costs - budgeted overhead costs = $197,200 - $189,400 = $7,800 unfavorable. The actual overhead expense was higher than the budgeted.
- controllable variance = (actual rate - standard rate) x actual units = ($176.07 - $189.40) x 1,120 units = -$14,929.60 favorable. The actual overhead rate was lower than the standard rate, that is why the variance is positive.
- volume variance = (standard activity - actual activity) x standard rate = (1,000 - 1,120) x $189.40 = -1,120 x $189.40 = -$212,128 favorable. More units where produced than budgeted, that is why the variance is positive.