Answer:
a) 749
b) 4.073
Step-by-step explanation:
Given:
Mean = demand = 80 pounds
Standard deviation of demand = 10 pounds
Lead time = 8 days
Standard deviation of lead time = 1 day
a) What ROP would provide a stock out risk of 10 percent during lead time.
To find this re-order point (ROP) quantity, take the formula:

Here, service level = 100%-10% = 90%,
Thus z at 90% = ±1.28


= 640 + 1.28* 84.85
= 748.61
≈ 749 units
b) What is the expected number of units (pounds) short per cycle.
Find the number of units shorts per cycle. Take the formula:

[
Where E(z) = standardized number of shorts = 0.048
= standard deviation of lead time demand = 84.85
Therefore,
E(n) = 0.048 * 84.85
= 4.073