Answer:
Predetermined manufacturing overhead rate= $42 per direct labor hour
Step-by-step explanation:
Giving the following information:
Estimated manufacturing overhead= $924,000
Estimated direct labor hours= 22,000
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 924,000/22,000
Predetermined manufacturing overhead rate= $42 per direct labor hour