Answer:
I strongly believe that NPV of the project is the requirement of this question:
NPV is -$486.82
Explanation:
The NPV is the present value of the future cash flows from year 1 through year 6 minus the initial capital investment of GH30,000
The cash flow discount factor =1/(1+r)^n
r is the opportunity cost of capital at 10%
n is the relevant year of each cash flow
NPV=-30,000+9000/(1+10%)^1+8000/(1+10%)^2+7000/(1+10%)^3+6000/(1+10%)^4+5000/(1+10%)^5+4000/(1+10%)^6=-$486.82
The project is not viable since NPV is negative