Answer:
600 minutes ( 10 hours)
Explanation:
rate c = 1 job/30 min
rate r = 1 job/40 mi
1 job / ( 1/30 + 1/40) = 1 / ( 7/120) = 17.14 minutes per ruckload
17.14 * 35 trucks = 600 minutes