160
Step-by-step explanation:
Reorder point is the inventory level at which new order are placed to prevent a down time due to stock out and and holding cost are also at the minimal level .
Workings
Annual demand = 8000
Ordering cost = $50
Holding cost = $20
Operating days = 250
Lead time =5 days
Re order point = Average daily usage * Average lead time
Average daily usage = 8000/250 = 32
Reorder point = 32*5 =160