Answer:
The estimated overhead cost if 225 direct labor hours are expected to be used in the upcoming period is $9,882.11
Step-by-step explanation:
In order to calculate the estimated overhead cost if 225 direct labor hours are expected to be used in the upcoming period we would have to make the following calculation:
Cost for 225 direct labor hours = Intercept + Slope*225
Cost for 225 direct labor hours=$596.36+ ($41.27*225)
Cost for 225 direct labor hours=$9,882.11
The estimated overhead cost if 225 direct labor hours are expected to be used in the upcoming period is $9,882.11