Answer:
1. $7.00
2. $49,000
3. $33,200
Step-by-step explanation:
1. The computation of predetermined overhead rate is shown below:-
Predetermined overhead rate = Estimated overhead ÷ Estimated machine hours
= $420,000 ÷ 60,000
= $7.00
2. The computation of total manufacturing overhead applied is shown below:-
Particulars Job 101 Job 102 Job 103 Total
Direct material $19,200 $14,400 $9,600 $43,200
Direct labor $28,800 $11,200 $9,600 $49,600
Manufacturing
overhead $7,000 $28,000 $14,000 $49,000
Total $55,000 $53,600 $33,200 $141,800
3. The computation of balance in the Work in Process Inventory account at the end of the first month is shown below:-
Particulars Job 101 Job 102 Job 103 Total
Direct material $19,200 $14,400 $9,600 $43,200
Direct labor $28,800 $11,200 $9,600 $49,600
Manufacturing
overhead $7,000 $28,000 $14,000 $49,000
Total $55,000 $53,600 $33,200 $141,800
Job 101 is completed and sold
Job 102 is completed and kept in finished goods inventory.
Job 103 is balance which indicates the work in progress.