Answer:
The expected completion time of this project from now is 2.5 months.
Explanation:
To find the expected completion time for the project, we multiply each projection by it's probability.
We have that:
0.4 = 40% probability it takes 2 months to complete the project.
0.3 = 30% probability that it takes 2.5 months to complete the project.
0.2 = 20% probability it takes 3 months to complete the project.
0.1 = 10% probability it takes 3.5 months to complete the project.
What is the expected completion time (in months) of this project from now?
E = 0.4*2 + 0.3*2.5 + 0.2*3 + 0.1*3.5 = 2.5
The expected completion time of this project from now is 2.5 months.