37.9k views
1 vote
Fred's Flooring (FF) contracted with Harry homeowner to install wood flooring throughout Harry's home. Harry was to purchase the flooring, and the contract was solely for installation. Payment was to be 20 percent at the time that the work commenced and 80 percent once the flooring was installed. Harry purchased the flooring materials and paid the 20 percent, so FF began work. When FF's work was halfway completed, Harry realized that he didn't have the money to pay FF on completion, so he bolted the doors and refused access. If FF wants to rescind the contract and be paid for work completed, FF would sue fora. Compensatory damagesb. Consequential damagesc. Restitutiond. Liquidated damages

1 Answer

5 votes

Answer:

c. Restitution

Step-by-step explanation:

In contract law, restitution (or restitutionary damages) is a legal remedy that applies to situations where an injured party sues another party in order to recover the same financial position as they were before the damages or injuries occurred. Generally restitution applies to civil cases and sometimes to criminal ones.

In this case, FF wants to recover work that has already been completed, they do not seek any other type of damages resulting from the breach of the contract. This is why restitution applies.

User Hubcaps
by
6.8k points