Answer:
The answer is option A
Step-by-step explanation:
Amount($) Activity cost pools Allocated amount($)
Wages and salaries 340,000 30% 102,000
Depreciation 160,000 15 % 24,000
Occupancy 220,000 15 % 33,000
Total 720,000 159,000
Cost driver (hours) 30,000 machine hours
Rate per machine hr 159,000 รท 30,000
=$ 5.30