Answer:
a) $1,470 Debit –Wage Expense; $1,470 Credit –Wage Payable.
b) $4,410 Debit –Wage Expense; $1,470 Debit –Wage Payable
Step-by-step explanation:
Remember, we are told each of the worker earns $210 per day. Therefore
a.To record accrued and current wages.Wages expense = 7 workers × 3 days × $210 = $4,410.
b. To record accrued wages four days Cash = 7 workers × 4 days × $210 = $5,880. For one day (7 workers × $210) = $1,470.