Answer: S1 = $ 7500 + 0.20 S2
Step-by-step explanation:
From the question, Howard Company has two support departments which are (S1 and S2) and two producing departments which are (P1 and P2). The department S1 costs are allocated on the basis of number of employees, and the department S2 costs are allocated on basis of space occupied expressed in square feet.
The algebraic equation expressing the total costs allocated from S1 is calculated as follow:
S1 Direct Cost = $ 7500
The cost of S2 will be allocated to S1 based on the space occupied and the total space that is occupied is:
= 1000 + 1500 + 2500
= 5000 sq ft
Space occupied by S1 = 1000
S2’s cost allocated to S1 will be:
= (1000 / 5000) of S2 cost
= 0.20 S2
Therefore the correct option is:
S1 = $ 7500 + 0.20 S2