Answer:
a)
y = $10x
b)
y = $15.6x
c)
y = $5000 + $0.3x
d)
y = $300000 + $100x
Step-by-step explanation:
y for estimated costs and X for activity of the cost driver. Linear cost function is given as:
y = a + bx.
Where y is the cost being predicted, x is the cost driver, a is the fixed cost (intercept) and b is the variable cost per unit (slope)
a) Since Direct manufacturing labor is $10 per hour, variable cost (b) = Direct manufacturing labor = $10
Therefore:
y = $10x
b) variable cost (b) = Direct materials cost = $15.60 per cubic yard.
Therefore:
y = $15.6x
c) Fixed cost (a) = utilities = $5000 and variable cost (b) = charges = $0.3 per kilowatt-hour. Therefore:
y = $5000 + $0.3x
d) Fixed cost (a) = Machine operating costs = $300000 and variable cost (b) = utility costs = $100 per day. Therefore:
y = $300000 + $100x