Answer:
$5400 Favorable
Step-by-step explanation:
Standard 2 hour at $15 per hour
Standard hours 2 hour per unit * 2900 units = 5800 hours
Total Standard cost = 5800 hours * $15 per hour = $87,000
Actual hours = 5100
Actual cost = $81600 / 5100 hours = $16 per hour
Variance = Standard - Actual
Labor hour Variance Favorable = 700 hours (5800 hours - 5100 hours)
Total Labor variance = $5400 ($87,000 - $81,600)