Answer:
Total cost= $5,000
Step-by-step explanation:
Giving the following information:
Job 731:
Direct Materials= $2,500
Direct Labor hours= 100
Direct Labor wage rate: $10.00 per hour
First, we need to calculate the direct labor cost and then allocate overhead:
Direct labor= 100*10= $1,000
Allocated overhead= 1,000*1.5= $1,500
Total cost= 2,500 + 1,000 + 1,500
Total cost= $5,000