234k views
5 votes
The company produced 5,600 units during the month.A total of 14,700 pounds of material were purchased at a cost of $41,160.There was no beginning inventory of materials on hand to start the month; at the end of the month, 2,940 pounds of material remained in the warehouse.During March, 3,000 direct labor-hours were worked at a rate of $19.50 per hour.Variable manufacturing overhead costs during March totaled $6,950. The direct materials purchases variance is computed when the materials are purchased. The materials quantity variance for March is:

User Rui Lopes
by
5.1k points

1 Answer

1 vote

Answer:

-$3,500 Unfavorable

Explanation:

For computation of materials quantity variance for March firstly we need to find out the standard quantity and actual quantity which is shown below:-

Standard quantity = Production units × Standard quantity of direct material

= 5,600 × 2.0

= 11,200

and

Actual quantity = Total pounds of material - Ending pounds of material

= 14,700 - 2,940

= 11,760

Now, we will put these value by using the formula of material quantity variance for march which is shown below:

Materials quantity variance for March = (Standard quantity - Actual quantity) × Standard price

= (11,200 - 11,760) × $6.25

= -$560 × $6.25

= -$3,500 Unfavorable

The unfavorable variance is the variance at which the actual cost is more than the standard cost and the same is to be considered

The company produced 5,600 units during the month.A total of 14,700 pounds of material-example-1
User Octopusgrabbus
by
5.1k points