Answer:
$21.42
Explanation:
The computation of fixed component in the predetermined overhead rate is shown below:-
Fixed component in the predetermined overhead rate = Fixed Overhead ÷ Machine Hours
= $87,822 ÷ 4,100
= $21.42
Therefore for computing the fixed component in the predetermined overhead rate we simply divide the fixed overhead by machine hours.
And all the other information i.e given is not relevant. Hence, ignored it